Structural and Piping works of LNG storage tanks
Client
IHI Corporation, Japan
Year
October, 2018
Services
Structural works, Piping
Industry
Liquefied Natural Gas (LNG)
External structure and piping works of two LNG Storage Tanks (including fabrication, erection, testing of carbon steel along with the galvanization of fire water system, stainless steel (cryogenic piping), structural steel fabrication and erection including blasting, painting, and NDT works, at Mundra LNG Terminal for GLL Limited, Adani Port, Gujarat.
Project Management Consultant: Whessoe Engineering Ltd.
Scope of work: Fabrication CS Piping Inch Dia (DB) -13097 DB & SS Piping Inch Dia (DB)- 14398 DB, Erection of piping IM33573, Structural steel and pipe support fabrication and erection – 584 MT approximately.
Peak Strength: 320 Nos (Staff and workmen)